Ascent Education Home
• CAT 2008 for IIMs
CAT - Intensive Contact Class @ Chennai
» CAT - Weekend Crash Course
» CAT - Correspondence
• India
• Abroad
» Mock CAT Series
» CAT - Math & DI Boot Camp
» Math Shortcut Workshops
• TANCET 2008 @ Chennai
• TANCET 2008 @ Kovai
• XAT 2008
• GRE-GMAT
• US B Schools
• Faculty List
• Question A Day

Work and Time - Quant/Math - CAT 2009

  1. Algebra
  2. Progressions
  3. Averages
  4. Clocks and Calendars
  5. Data Sufficiency
  6. English Grammar
  7. Function
  8. Geometry
  9. Interest
  10. Mensuration
  11. Mixtures & Alligations
  12. Number System
  13. Percentages
  14. Permutation & Combination
  15. Pipes & Cisterns And Work & Time
  16. Probability
  17. Profit & Loss
  18. Races
  19. Ratio, Proportion
  20. Speed, Time & Distance
  21. Trigonometry
  22. Miscellaneous
  23. General Knowledge
Question 4 the day: May 8, 2003

The question for the day is from the topic of Work and Time.
2 men and 3 boys can do piece of work in 10 days and 3 men together with 2 boys can do the same job in 8 days. In how many days can 2 men and a boy do the work?

(1) 12½ days (2) 18½ days
(3) 25 days (4) 25½ days
Correct Answer - (1)

Solution:

10 (2 men + 3 boys) = 8 (3 men + 2 boys)
=> 4 men = 14 boys or 2 men = 7 boys
Now 2 men + 3 boys = 10 boys
And 2 men + 1 boy = 8 boys
=> 10 boys can do a job in 10 days
Therefore, 8 boys can do a job in or 12 ½ days.