Ascent Education Home
• CAT 2008 for IIMs
CAT - Intensive Contact Class @ Chennai
» CAT - Weekend Crash Course
» CAT - Correspondence
• India
• Abroad
» Mock CAT Series
» CAT - Math & DI Boot Camp
» Math Shortcut Workshops
• TANCET 2008 @ Chennai
• TANCET 2008 @ Kovai
• XAT 2008
• GRE-GMAT
• US B Schools
• Faculty List
• Question A Day

Work and Time - Quant/Math - CAT 2009

  1. Algebra
  2. Progressions
  3. Averages
  4. Clocks and Calendars
  5. Data Sufficiency
  6. English Grammar
  7. Function
  8. Geometry
  9. Interest
  10. Mensuration
  11. Mixtures & Alligations
  12. Number System
  13. Percentages
  14. Permutation & Combination
  15. Pipes & Cisterns And Work & Time
  16. Probability
  17. Profit & Loss
  18. Races
  19. Ratio, Proportion
  20. Speed, Time & Distance
  21. Trigonometry
  22. Miscellaneous
  23. General Knowledge
CAT Sample Questions - Question 4 the day : June 15, 2004

The question for the day is from the topic Work and Time..

Ram, who is half as efficient as Krish, will take 24 days to complete a work if he worked alone. If Ram and Krish worked together, how long will they take to complete the work?

(1) 16 days   (2) 12 days
(3) 8 days   (4) 18 days

Correct choice - (3) Correct Answer -(8 days)

Explanatory Answer

Ram takes 24 days to complete the work, if he works alone.
As Krish is twice as efficient as Ram is, Krish will take half the time to complete the work when Krish works alone, i.e., in 12 days.

Ram completes th of the work in a day.
Krish completes th of the work in a day.
When they work together, they will complete th work in a day.
Therefore, when they work together they will complete the work in 8 days.