Ascent Education Home
• CAT 2008 for IIMs
CAT - Intensive Contact Class @ Chennai
» CAT - Weekend Crash Course
» CAT - Correspondence
• India
• Abroad
» Mock CAT Series
» CAT - Math & DI Boot Camp
» Math Shortcut Workshops
• TANCET 2008 @ Chennai
• TANCET 2008 @ Kovai
• XAT 2008
• GRE-GMAT
• US B Schools
• Faculty List
• Question A Day

Time and Work - Quant/Math - CAT 2009

  1. Algebra
  2. Progressions
  3. Averages
  4. Clocks and Calendars
  5. Data Sufficiency
  6. English Grammar
  7. Function
  8. Geometry
  9. Interest
  10. Mensuration
  11. Mixtures & Alligations
  12. Number System
  13. Percentages
  14. Permutation & Combination
  15. Pipes & Cisterns And Work & Time
  16. Probability
  17. Profit & Loss
  18. Races
  19. Ratio, Proportion
  20. Speed, Time & Distance
  21. Trigonometry
  22. Miscellaneous
  23. General Knowledge
Question 4 the day: June 13, 2003

The question for the day is from the topic of Time and Work.
X alone can do a piece of work in 15 days and Y alone can do it in 10 days. X and Y undertook to do it for Rs. 720. With the help of Z they finished it in 5 days. How much is paid to Z?

(1) Rs. 360 (2) Rs. 120
(3) Rs. 240 (4) Rs. 300
Correct Answer - (2)

Solution:


In one day X can finish 1/15th of the work.

In one day Y can finish 1/10th of the work.

Let us say that in one day Z can finish 1/Zth of the work.

When all the three work together in one day they can finish 1/15 + 1/10 + 1/Z = 1/5th of the work.

Therefore, 1/Z = 1/30.

Ratio of their efficiencies = 1/15: 1/10: 1/30 = 2: 3: 1.Therefore Z receives 1/6th of the total money.

According to their efficiencies money is divided as 240: 360: 120.

Hence, the share of Z = Rs. 120.