Ascent Education Home
• CAT 2008 for IIMs
CAT - Intensive Contact Class @ Chennai
» CAT - Weekend Crash Course
» CAT - Correspondence
• India
• Abroad
» Mock CAT Series
» CAT - Math & DI Boot Camp
» Math Shortcut Workshops
• TANCET 2008 @ Chennai
• TANCET 2008 @ Kovai
• XAT 2008
• GRE-GMAT
• US B Schools
• Faculty List
• Question A Day

Work and Time - Quant/Math - CAT 2009

  1. Algebra
  2. Progressions
  3. Averages
  4. Clocks and Calendars
  5. Data Sufficiency
  6. English Grammar
  7. Function
  8. Geometry
  9. Interest
  10. Mensuration
  11. Mixtures & Alligations
  12. Number System
  13. Percentages
  14. Permutation & Combination
  15. Pipes & Cisterns And Work & Time
  16. Probability
  17. Profit & Loss
  18. Races
  19. Ratio, Proportion
  20. Speed, Time & Distance
  21. Trigonometry
  22. Miscellaneous
  23. General Knowledge
Question 4 the day: June 19, 2002
The question for the day is from the topic - Work and Time.
Shyam can do a job in 20 days, Ram in 30 days and Singhal in 60 days. If Shyam is helped by Ram and Singhal every 3rd day, how long will it take for them to complete the job?
(1)12 days (2)16 days (3)15 days (4)10 days
Correct Answer - (3)

Solution:

As Shyam is helped by Ram and Singhal every third day, Shyam works for 3 days while Ram and Singhal work for 1 day in every 3 days.

Therefore, the amount of work done in 3 days by Shyam, Ram and Singhal = th of the job. Hence, it will take them 5 times the amount of time = 3*5 = 15 days.